Motion Settings

Any given motion profile can be plotted as a trapezoid, where Time is the base, Velocity is the height, acceleration rate is the angle and Distance is the area.

By default, the Nippon Pulse controllers use a linear acceleration profileLinear acceleration as shown below.  To reduce jerk, an S-curve acceleration profile (SCV) can also be used.  The percentage of S-curve can also be adjusted (JKA, JKD). 

For a typical move, the axis will start moving at the low-speed setting (LSPD) and accelerate (ACC) to the high-speed setting (HSPD). Once at high-speed, the motor will move at a constant speed until it decelerates (DEC) from high-speed to low-speed and immediately stops. 

The motion profile can be performed as an absolute move (ABS) from a homed location or incremental move (INC) from the current position. The MM command can be used to determine the current move mode of the controller.

For more information on the settings, see the following sections in the Commander manual:


Command

Description

Available with:

Link

ASCII

Standalone

CMD-4CR

PMX-4EX

PMX-4ET

PMX-2ED

PMX-2EX

ABS

ABS

Absolute position coordinate mode

ABS

ACC

ACC

Acceleration time in ms

ACC

DEC

DEC

Deceleration time in ms

DEC

HSPD

HSPD

High speed setting



HSPD

HS

HSPD




INC

INC

Incremental position coordinate mode

INC

JKA

--

Jerk control for acceleration in %





JKA

JKD

--

Jerk control for deceleration in %





JKD

LSPD

LSPD

Low speed setting



LSPD

LS

LSPD




MM

--

Position coordinate mode status


MM

SCV

SCV

S-curve acceleration enable/disable

SCV

The black dots indicate the command is available for the listed controller family.